| Order | G.O.(Ms) No.185 |
|---|---|
| Department | Municipal Administration and Water Supply Department |
| Official title | Municipal Administration and Water Supply Department – Guidelines for Rejuvenation of Water Bodies by Corporates / Firm / Non-Governmental Organizations / Community Based Organizations / Educational Institutions subject to the restrictions issued in the G.O. (Ms) No. 50, Industries (MMC-1) Department, dated 27.04.2017 and further amendments issued thereon – Approved – Orders Issued. |
| Listed on the official site | 16 October 2026 |
| Pages | 16 |
| Official PDF | Open the PDF on tn.gov.in |
Text of the order
Read this first. This text was read from the PDF by computer, not typed by a person. Most Government Orders are scanned pages, so names, numbers, amounts and Tamil text can be read wrongly or left out. The official PDF is the authority: check anything you rely on against it.
Show the text (35,841 characters). Read from scanned pages by optical character recognition.
PDF page 1ABSTRACT
Municipal Administration and Water Supply Department – Guidelines for
Rejuvenation of Water Bodies by Corporates / Firm / Non-Governmental
Organizations / Community Based Organizations / Educational Institutions
subject to the restrictions issued in the G.O. (Ms) No. 50, Industries
(MMC-1) Department, dated 27.04.2017 and further amendments issued
thereon – Approved – Orders Issued,
Municipal Administration and Water Supply (MA.5(2)) Department
G.O (Ms) No. 185 Dated: 16.10.2026
AGearst@nannairG 2057
WB uTTUeL a1g5Lib,
yma 29
Read:
From the Director of Municipal Administration {etter Roc No.
22106/2026/G, dated 06.10.2026.
ACO CK
ORDER:
In the letter read above, the Director of Municipal Administration
has stated that, there are approximately 1,931 water bodies under the
Corporations and Municipalities and over 2,253 water bodies in Town
Panchayats. These waterbodies are under the maintenance of concerned
Local bodies and have been rejuvenated through various Government
schemes,
2. To supplement Government efforts, Corporate Social
Responsibility (CSR) of Companies, Non-Governmental Organisations
(NGOs) and Public Contributions were leveraged through Public –
Participatory Namakku Name Thittam (NNT) Scheme.
3. Despite these restoration efforts, a significant number of water
bodies have not yet been restored to their original storage capacity and
require further rejuvenation and conservation measures.
4. Hence, the Director of Municipal Administration has requested the
Government to approve the guidelines which are enclosed in the
Annexure-I for the Rejuvenation of Water Bodies by Corporates / Firms /
Non-Governmental Organizations (NGOs)/ Community Based
Organizations (CBOs) / Educational Institutions subject to the restrictions
issued in the G.O.(Ms) No. 50, Industries (MMC-1) Department,
dated 27.04.2017 and further amendments issued thereon.
5. The Government, after careful examination of the proposal of the
Director of Municipal Administration, have decided to accept the proposal
of Director of Municipal Administration and approve the guidelines which
are in the Annexure-I for the Rejuvenation of Water Bodies by Corporates
/ Firms / Non-Governmental Organizations (NGOs)/ Community Based
Organizations (CBOs) / Educational Institutions subject to the restrictions
issued in the G.O.(Ms) No. 50, Industries (MMC-1) Department,
dated 27.04.2017 and further amendments issued thereon.
6. The Government also authorise the Corporation / Municipal
Commissioner concerned for Corporation / Municipality and Assistant
Director (Town panchayats) concerned for Town Panchayats to sign the
Memorandum of Understanding (MoU) with the organisation concerned as
per the format in Annexure-II. A work completion certificate in
Annexure-III is also enclosed.
(BY ORDER OF THE GOVERNOR)
GAGANDEEP SINGH BEDI,
ADDITIONAL CHIEF SECRETARY TO GOVERNMENT
To:
The Commissioner, Greater Chennai Corporation, Chennai – 600 003.
The Director of Municipal Administration, Chennai – 600 028.
The Director of Town Panchayats, Chennai – 600 028.
The Principal Accountant General, Chennai – 600 018.
The Pay and Accounts Officer (North), Chennai ~ 600 035.
The Commissioner, Treasuries and Accounts, Chennai – 600 035.
The District Treasury Officers (concerned), Chennai – 600 009.
Copy to: –
Hon’ble Chief Minister Office, Chennai – 600 009.
The Special Personal Assistant to Hon’ble Minister for Schoo! Education,
Tamil Development, Information and Publicity, Chennai – 600 009.
The Principal Private Secretary to Additional Chief Secretary to Government,
Municipal Administration and Water Supply Department, Chennai – 600 009.
The Finance (Infra – IV/BG.II/Res-II/W&M-I) Department, Chennai – 600 009.
The Municipal Administration and Water Supply Department (OP-II) Department,
Chennai — 600 009.
/ {FORWARDED BY ORDER//
r
—
Pes Sebo
€
ANNEXURE -T
(G.0.(Ms) No. 185, Municipal Administration and Water Supply
Department, dated 16.10.2026)
Guidelines for Rejuvenation of Water Bodies by Corporates/Firms/
NGOs/CBOs/Educational Institutions subject to the restrictions
issued in the G.O.(Ms) No.50, Industries (MMC-1) Department,
dated 27.04.2017 and further amendments issued thereon.
1. Introduction
There are approximately 1,931 water bodies under the Corporations
and Municipalities and about 2,253 waterbodies in Town Panchayats.
These waterbodies are managed by the concerned local bodies. These
water bodies have been rejuvenated through various Government
schemes. Despite these restoration efforts, a significant number of water
bodies have not yet been restored to their original storage capacity and
require further rejuvenation and conservation measures.
The State largely depends on monsoon rainfall for replenishment of
its water resources. Any deficiency or failure of the monsoon often results
in water scarcity, reduced groundwater recharge and drought conditions,
adversely affecting drinking water supply and urban livelihood. To
supplement Government efforts, Corporate Social Responsibility (CSR)
funds of Companies, Non-Governmental Organisations (NGOs),
Community Based Organisations (CBOs) and Educational Institutions may
be leveraged for the rejuvenation and conservation of water bodies.
2. Objective
e To restore the Water bodies to their original capacity.
* To ensure increase in ground water recharge and increase in Ground
Water Level (GWL).
* To put in place flood mitigation measures by preventing surplus runoff
and breaches in the water bodies.
¢ To regulate storage of water for drinking and agricultural purposes,
thereby ensuring sustainable drinking water supply and increasing the
crop productivity and area irrigated.
* To enhance the capacity of Water bodies as part of Disaster
Management efforts towards both floods and drought.
3. Scope of Works
° Desilting and deepening of water bodies.
¢ Desilting and restoration of supply, inlet and outlet channels.
* Removal of jungle growth, bushes, shrubs, invasive vegetation,
garages and other debris from water body area and bund slopes.
Strengthening, sectioning and consolidation of bunds.
Restoration of bunds to the original cross-section and approved slope.
Restoration of sluices, surplus weirs and related hydraulic structures.
Prevention of waste water contamination.
4. Selection of Works
Water bodies that have been rejuvenated or restored during the
preceding three years (i.e. completion of the sanctioned work) under
Government schemes such as AMRUT, I&A, AMRUT 2.0, CGF, 15" CFC,
KNMT NNT or any other funding source, shall not be eligible.
5. Modes of Implementation
The above works may be taken up as per the following modes:
e Mode A: Funded and Executed by Corporates/ Firms/ NGOs/ CBOs/
Educational Institutions
e Mode B: Works Executed by the Department with Funding from
Corporates/ Firms/ NGOs/ CBOs/ Educational Institutions
« Mode C: Machineries and kind provided by Corporates/ Firms/ NGOs/
CBOs/ Educational Institutions
« Mode D: Executed through modalities detailed under G.O.(Ms) No.50
of Industries (MMC-1) department dated 27.04.2017 and further
amendments.
5. A. Funded and Executed by Corporates / Firms / NGOs / CBOs /
Educational Institutions
e The Corporates/ Firms/ NGOs/ CBOs/ Educational Institutions intending
to undertake the rejuvenation of a water body shall submit their
proposal to the Commissioner, Greater Chennai Corporation / Director
of Municipal Administration /Director of Town Panchayats.
« The Commissioner, Greater Chennai Corporation / Director of Municipal
Administration /Director of Town Panchayats shall forward the proposal
to the respective Assistant Commissioner / Deputy Commissioner (in
case of Greater Chennai Corporation), Commissioner/ Executive Officer
(in case of Corporations/ Municipalities/Town Panchayats) of the
concerned Zone/ ULBs for field verification and technical examination.
« The Assistant Commissioner/ Deputy Commissioner (in case of Greater
Chennai Corporation), Commissioner/ Executive Officer of the
concerned Zone/ULBs shall conduct a field inspection of the proposed
water body and submit recommendations to the Commissioner, Greater
Chennai Corporation / Director of Municipal Administration /Director of
Town Panchayats (directly in case of Corporations (incl. Greater
Chennai Corporation), through Regional Director of Municipal
Administration for Municipalities and through concerned Assistant
Director for Town Panchayats) either by accepting the proposal or
returning it with specific observations and remarks within 15 days from
the date of receipt of the proposal.
* Based on the recommendations, The Commissioner, Greater Chennai
Corporation / Director of Municipal! Administration /Director of Town
Panchayats shall direct the Assistant Commissioner/ Deputy
Commissioner (in case of Greater Chennai Corporation), Commissioner/
Executive Officer (in case of Corporations/ Municipalities/ Town
Panchayats) of the concerned Zone / ULBs to issue a
No Objection Certificate (NOC) for the commencement of the
rejuvenation work within 7 days.
e The department shall provide technical guidance for preparing the
Detailed Project Report (DPR) and after approval, for the execution of
the work. :
« After that, a Memorandum of Understanding (MoU) may be executed
by concerned Corporate/ Firm/ NGO/ CBO/ Educational Institution with
the Urban Local Body concerned.
e Upon issuance of the NOC and signing of the Memorandum of
Understanding (MoU), the Corporate/ Firm/ NGO/ CBO/ Educational
Institution funded work shall commence immediately and be completed
within three months from the date of execution of the MoU.
« The implementation schedule shall be planned to ensure that the works
are completed well before the onset of the monsoon season, thereby
preventing delays due to adverse weather conditions and enabling
effective storage and conservation of rainwater.
5. B. Works Executed by the ULB with Funding from Corporates /
Firms / NGOs / CBOs / Educational Institutions
If Corporates/ Firms/ NGOs/ CBOs/ Educational Institutions request that
the works may be executed by the Urban Local Bodies, the following
procedure is to be adhered:
5.B.1. Estimate Preparation:
The estimates and Detailed Project Report shall be prepared by the
concerned Engineer as per the Schedule of Rates (SoR). The Assistant
Commissioner/ Deputy Commissioner (in case of Greater Chennai
Corporation), Commissioner/ Executive Officer (in case of
Corporations/ Municipalities/Town Panchayats) should inspect the site
before according Administrative Sanction. The Engineers concerned of
the Urban Local Body shall exclusively inspect and verify the works
proposed in the field, check the correctness of the estimates.
5.B.2.Administrative Sanction
Administrative Sanction shall be accorded by the competent Authority
under the Tamil Nadu Urban Local Bodies Rules, 2023 & updated
instructions.
5.B.3. Technical Sanction:
Technical sanction will be accorded by the competent authority as per
the Tamil Nadu Urban Local Bodies Rules, 2023 & updated instructions.
5.B.4. Tendering:
The works will be executed by following the Tamil Nadu Transparency
in Tenders Act, 1998 and Rules 2000. e-Tender mode will be followed
for all the works.
5.B.5. Execution of Work:
The works shall be executed as per the technical standard (given in
clause 6.2) and execution (given in clause 6.3).
5.B.6. Flow of Funds:
The funds provided by Corporate Social Responsibility of Corporates /
Firms /NGOs/CBOs/Educational Institutions will be with Assistant
Commissioners/ Deputy Commissioners (in case of Greater Chennai
Corporation), Commissioners/ Executive Officers (in case of Corporations/
Municipalities/Town Panchayats).
The Assistant Commissioners/ Deputy Commissioners (in case of
Greater Chennai Corporation), Commissioners/ Executive Officers (in case
of Corporations/ Municipalities/Town Panchayats) shall open a separate
account at the ULB level and all payments to the vendors shall be done
through this account.
5.C. Machineries Provided by Corporates / Firms / NGOs / CBOs /
Educational Institutions
If Corporates /Firms /NGOs /CBOs /Educational Institutions provide
Machineries, the following procedure is to be adhered:
« The Corporates/Firms/NGOs/CBOs/Educational Institutions shall
provide the required machinery or any other kind at free of cost for the
approved rejuvenation works.
« If fuel charges, skilled and unskilled labour are borne by another
Corporate/ Firm/ NGO/ CBO/ Educational Institution, then the works
shall be executed by ULB with fund tie-up with two or more parties.
e The estimate shall be prepared by the ULB Engineer for assessing the
time and fuel required for utilizing machinery based on the quantity to
be desilted at site. The same_ shall be _ intimated to
Corporates/Firms/NGOs/CBOs/Educational Institutions.
e A proceeding shall be issued by the Assistant Commissioner/ Deputy
Commissioner (in case of Greater Chennai Corporation), Commissioner/
Executive Officer (in case of Corporations/ Municipalities/Town
Panchayats) mentioning quantity of fuel required, machinery details,
working hours and labour requirement.
« The works shall be monitored and executed under the supervision of
the Technical Officers (Assistant Engineer /Assistant Executive Engineer
/Executive Engineer / Superintending Engineer / Chief Engineer) and
compieted within the stipulated time.
« M-book along with proper hourly logbook of machineries, daily records
of machinery utilization, fuel consumption, and labour engagement
shall be maintained by the department officials.
¢ Joint inspection may be done by the department officials along with
Corporates/Firms/NGOs/CBOs/Educational Institutions.
e Documentation along with Geo-tagged photographs shall be carried out
by the department officials.
5.D Desilting of Water Bodies under G.O. (Ms) No.50, Industries
(MMC-1) Department, dated 27.04.2017 and further amendments
issued thereon.
The Assistant Commissioners/ Deputy Commissioners {in case of
Greater Chennai Corporation), Commissioners/ Executive Officers (in case
of Corporations/ Municipalities / Town Panchayats) should convene
co-ordination meeting with ail the stake holder Departments to identify
and finalize the list of waterbodies, proposed for removal of clay/silt
/earth. (such waterbodies should not be taken up for the desilting through
Schemes / Corporate Social Responsibility funds etc.,)
The following points to be noted before commencement of work:
a) The Assistant Commissioners/ Deputy Commissioners (in case of
Greater Chennai Corporation), Commissioners/ Executive Officers (in
case of Corporations/ Municipalities/Town Panchayats) to oversee the
compilation of the list of waterbodies and ensure that the water bodies
belong to Municipal Administration and Water Supply Department.
b) Care should be taken not to damage the bund during the removal of
clay and silt.
c) In the case of waterbodies which are utilised for irrigation, the level
should be maintained to ensure smooth flow of water to the fields. It
should not go below Sill Level of the tank.
d) The depth of excavation should not exceed the permissible limit.
e) Prior permission shall be obtained from the Tahsildar for removal of
such quantity of silt from the waterbodies and the period of permission
shall not exceed 30 days.
f) Concerned officials should monitor the process cautiously and there
should not be any deviation from the Government Orders and
Guidelines.
g) The farmers shail arrange for removal and conveyance at their own
cost as indicated in Appendix to G.O.(Ms.) No.50, Industries (MMC.1)
Department, dated:27.04.2017 and this shall be monitored by the
District Collectors.
h) An official is to be nominated to monitor the desilting of water
bodies at the ULB level.
i) City Engineer/ Superintending Engineer/ Executive Engineer /
Assistant Executive Engineer / Assistant Engineer to ensure that the
guidelines mentioned in the SoP is followed during desilting of
waterbodies.
6.1. Participatory Approach
Welfare associations may be involved for desilting of water bodies.
6.2. Technical Standards
All works shail be executed strictly in accordance with the Public Works
Department (PWD) Schedule of Rates (SoR).
6.2.1 Technical Specifications
* Identification and marking of boundary of the water body as per the
actual extent in the FMB sketch.
* Boundary stones shall be fixed to clearly delineate the extent of the
water body and to avoid any encroachments in the future.
° The FMB sketch and other details that may be required for the
Preparation of project report shall be collected from the Town
Surveyor.
¢ Topographical survey of the water body shall! be carried out using Auto
levels/Total Station etc. The reference benchmarks shall be
e established. Tank Bund Level (TBL), Full Tank Level (FTL), Maximum
Water Level (MWL) shall be marked on the relevant places.
e Contour survey with a 10m x 10m grid shall be carried out covering
the entire water spread area.
« This shall be followed by carrying out levels of the cross and
longitudinal! sections of the Tank Bund at an interval of 30m.
¢ The Contour map should be plotted to the required scale and the
quantum of earth work to be done shall be worked out based on the
current storage capacity and the original storage capacity.
¢ Similarly, the quantum of earth work required to be deposited on the
tank bund to restore it to its original cross section should be assessed.
» The contour mapping, details of pre-levels, earth work calculation sheet
etc. duly certified by the Assistant Engineer/Assistant Executive
Engineer shail be submitted to the Chief Engineer for corporations,
Regional Executive Engineer for Municipalities and Executive Engineer
for Town Panchayats.
« The total quantity of silt to be excavated from the water body is to be
assessed. The depth of silt shall be assessed judiciously, ensuring that
there will be no depletion of water body after de-siltation.
¢ The excavation of de-siltation bed may be in uniform gradient between
FTL contour and sluice sill level.
« Desilting/Deepening of Inlet/Outlet channels shall also be taken up so
that the surplus water can flow from one water body to other water
body.
e Provision for dead storage in the form of trenches running parallel to
the bund at a distance of 40m or 5 times the height of the bund from
the toe of the bund shall be provided, keeping the depth not exceeding
0.60m subject to a depth of 45 cm above sandy/permeable layer. The
size of the trenches shall be decided by the field Engineers.
6.2.2 Detailed Project Report (DPR) for the Desilting of
Waterbodies
« In general, the DPR may consist of the following (this is indicative
only).
Memoir containing the Hydraulic particulars of the Water body.
Trial pit particulars.
FMB Sketch.
L.S and C.S of the bund.
Pre-measurement particulars and contour drawings (coloured) of the
proposed site should compulsorily be part of the estimate.
Earthwork calculation sheet.
e Reduced levels to be furnished wherever necessary.
¢ Certificate specifying that the proposed work has not been executed for
the past three years under any Government Scheme.
Photos of all the components taken up in the estimate (inlet channel,
outlet channel, inlet and outlet, proposed deepening site, section of the
bunds with or without revetment, etc.).
Rate Analysis, Detailed Estimate, and Abstract Estimate.
6.3 Execution of Works
Technical standards to be followed during execution:
Jungle/Garbage Clearance shall be done on the entire extent of water
spread area and disposed properly away from the site. Heavy Jungle
shall be uprooted completely without leaving any stumps using
machinery. In the case of karuvel trees etc., proper auctioning shall be
done by following due procedures and the sale proceeds shall be
remitted into the ULB.
The Jungle growth, bushes, roots, on the upstream and downstream
slopes of the bund shall be removed completely.
Desiiting and Deepening of the water spread area and the supply
channels including removal of heavy Jungle in the water spread area
shall be done using machineries and by adopting the Public Works
Department (PWD) schedule of rates (SoR).
In case of bigger water bodies, desilting / deepening of the outer pond
and baby pond:
outer pond depth should be arrived based on the existing depth
and the baby pond which is half the length and half the breadth of
the main pond, should be dug up. If the pond is very large, the size
of the pond may be decided according to the local conditions. The
baby pond along with lead channel should be dug up to a depth of
minimum 1 metre beneath the level of main pond subject to depth
of 45cm above sandy/permeable layer.
Depth of excavation shall be done upto the original levels and shall be
pre-marked at site before commencement of earth work.
Reference Benchmarks shall be established on both directions of the
water body to cross verify the depth of excavation, particularly in sluice
head wall and permanent tree outside the water spread area.
Small Vertical Pillars (Thandoos) should be left at proper intervals to
verify the depth of completed excavation.
Proper benching of the existing slope should be done for effective
bonding of the fresh earth placed over the old embankment. The
dimensioning of benches shall normally be 30 cm x 30 cm or 45 cm x
45 cm or more.
Sectioning, Strengthening and consolidation of the bund using the
excavated earth and to restore the bund to the required cross section
through machineries like JCB, Power Roller and Tipper/Tractor, etc.
During earth filling on the bunds, extra width of 30 cm or more is to be
laid to ensure full compaction of designed section. Provision of this
extra earth fill, and its later trimming to the designed slope.
e Compaction of earth fill in layers of 25 cm thickness over the bund shall
be done to 95% Proctor density (OMC). Mechanized compacting
equipment such as power rollers, vibratory rollers, plate compactors
shall be used taking into consideration the top width of the bund.
e The top width and both side slopes shall be maintained based on the
height of the bund and the nature of soil.
« Restoring the bund to its original cross section and slope 1.5:1 for
Upstream Side and 2:1 for Downstream Side.
¢ Desilting/Deepening of Inlet/Outlet channels should also be taken up so
that the surplus water can flow from one tank to another tank. In case
of stand alone Water body, inlet and outlet channels should be desilted
at least for the length of 100m.
6.4 Disposal of Excavated Material
The excess excavated clay, silt, savudu and gravel shall be given free of
cost to the farmers for agriculture, public for domestic purpose and
potters. The cost for this excess quantity should not be added in the
Estimate cost of the works.
6.5 Monitoring and Quality Control
¢ The Commissioner in case of Corporation and Regional Director of
Municipal Administration / Assistant Director (Town Panchayats) in case
of Municipalities / Town Panchayats shall monitor implementation.
¢ Nodai officers in the cadre of Additional Director of Municipal
Administration / Chief Engineer /Superintending Engineer shall be
deputed for inspections periodically.
6.6 Documentation and Reporting
Proper documentation of the works should be done capturing various
processes in the implementation of scheme starting from selection of
works till the completion of works.
¢ High Resolution Photographs and videos of the site before, during and
after completion of works should be taken and properly documented.
¢ Work completion certificate enclosed in Annexure-II should be
documented for the completed works.
The Additional Chief Secretary to Government, Municipal Administration
and Water Supply Department is empowered to modify these guidelines in
consultation with the Commissioner, Greater Chennai Corporation,
Director of Municipal Administration and Director of Town Panchayats as
and when required.
GAGANDEEP SINGH BEDI,
ADDITIONAL CHIEF SECRETARY TO GOVERNMENT
//TRUE COPY//
ANNEXURE – IT
(G.O.(Ms) No. 185, Municipal Administration and Water Supply
Department, dated 16.10.2026)
Memorandum of Understanding (MoU) between
Corporates/Firms/ NGOs / CBOs/ Educational Institutions and
ULBs.
This Memorandum of Understanding (MoU) is made and entered into
on this day of month of year by and between
Corporate Social Responsibility having its Head
Office at (hereinafter referred to as
Corporates/Firms / Non-Governmental Organizations (NGOs)/ Community
Based Organizations (CBOs) / Educational Institutions) which term shall
include its successors, affiliates and assigns of ONE PART AND the
Assistant Commissioner/ Deputy Commissioner (of Greater Chennai
Corporation), Commissioner/ Executive Officer (in case of Corporation/
Municipality/ Town Panchayat) having its Office at
(hereinafter referred to as ULB) which term shall
include its successors, affiliates and assigns of the OTHER PART.
WHEREAS, the Assistant Commissioner/ Deputy Commissioner,
Commissioner/ Executive Officer, is responsible
for the development of urban areas in ULB,
including the rejuvenation of water bodies;
NOW, THEREFORE, in consideration of the foregoing premises and
the mutual covenants hereinafter set forth, the parties hereto agree as
follows:
1. Objective
The objective of this MoU is to establish a framework for collaboration
between the ULB, Greater Chennai Corporation (Zone)/
Corporation / Municipality/Town Panchayat and the Corporates/Firms/
Non-Governmental Organizations (NGOs) / Community Based
Organizations (CBOs) / Educational Institutions for the rejuvenation of
water bodies in District for a period of 3 months
commencing from the date of execution of this MoU (the “Project Period").
2. Scope of work
¢ Desilting and deepening of water bodies.
e Desilting and restoration of supply, inlet and outlet channels.
e Removal of jungle growth, bushes, shrubs and invasive vegetation
from water body area and bund slopes.
e Strengthening, sectioning and consolidation of bunds.
e Restoration of bunds to the original cross-section and approved slope.
* Restoration of sluices, surplus weirs and related hydraulic structures.
3. Responsibilities of the ULB, Greater Chennai
Corporation (Zone)/ Corporation/ Municipality/Town Panchayat.
To Provide Hydraulic particulars and land details with FMB of Water
body for the effective outcome of the project.
To Provide technical guidance and support to the Corporates/ Firms/
Non-Governmental Organizations (NGOs) / Community Based
Organizations (CBOs) /Educational Institutions for the implementation
of the Project.
To Facilitate necessary permissions and clearances from relevant
authorities for the execution of rejuvenation work.
To conduct monitoring visits to assess the progress of the Project.
4. Responsibilities of the Corporates/Firms/ Non-Governmental
Organizations (NGOs) / Community Based Organizations (CBOs)
/Educational Institutions
To prepare the estimates as follows:
Identification and marking of boundary of the water body as per the
actual extent in the FMB sketch.
Topographical survey of the water body shall be carried out using
Auto levels/Total Station etc. The reference benchmarks shall be
established. Tank Bund Level (TBL), Full Tank Level (FTL), Maximum
Water Level (MWL) shall be marked on the relevant places.
Contour survey with a 10m x 10m grid shall be carried out covering
the entire water spread area.
This shall be followed by carrying out levels of the cross and
longitudinal sections of the Tank Bund at an interval of 30m.
The Contour map should be plotted to the required scale and the
quantum of earth work to be done shall be worked out based on the
current storage capacity and the original storage capacity.
Similarly, the quantum of earth work required to be deposited on the
tank bund to restore it to its original cross section should be
assessed,
The contour mapping, details of pre-levels, earth work calculation
sheet etc., duly certified by the Assistant Engineer/Assistant
Executive Engineer shall be submitted to the Chief Engineer for
corporations, Regional Executive Engineer for Municipalities and
Executive Engineer for Town Panchayats.
The excavation of de-siltation bed may be in uniform gradient
between Full Tank Level contour and sluice sill level.
Desilting/Deepening of Inlet/Outlet channels shall also be taken up so
that the surplus water can flow from one water body to other water
body.
Jungle clearance should be done wherever necessary.
Provision for dead storage in the form of trenches running parallel to
the bund at a distance of 40m or 5 times the height of the bund from
the toe of the bund shall be provided, keeping the depth not
exceeding 0.60m subject to a depth of 45 cm above sandy/
permeable layer. The size of the trenches shail be decided by the field
Engineers.
Desilting & deepening of water spread area, Desilting of linking
channel and Strengthening & Consolidation of bund, will be
implemented with the technical guidance of department.
In case of waterbodies of the outer pond and baby pond outer pond
depth should be arrived based on the existing depth and the baby
pond which is half the length and half the breadth of the main pond,
should be dug up. If the pond is very large, the size of the pond may
be decided according to the local conditions. The baby pond along
with lead channel should be dug up to a depth of minimum 1 metre
beneath the level of main pond subject to depth of 45cm above
sandy/permeable layer.
To Employ qualified personnel and utilize appropriate technologies for
the rejuvenation work.
Proper documentation of the works should be done capturing various
processes in the implementation of scheme starting from selection of
works to till the completion of works. Photographs of the site before,
during and after completion of works should be taken and properly
documented.
5. Terms of Reference
Ensure that the project is handled only by the authorized
representatives of the Parties, as Corporates/Firms/ Non-
Governmental Organizations (NGOs) / Community Based
Organizations (CBOs) /Educational Institutions. No unauthorized
person shall be involved in the implementation of the project.
Ensure that the earth excavated from the waterbody, as a part of the
rejuvenation work, shall be exclusively used for the consolidation of
the bunds, and shall not be used for any other purpose.
The excess excavated clay, silt, savudu and gravel shall be given free
of cost to the farmers for agriculture, public or domestic purpose and
potters. The cost for this excess quantity should not be included in
the cost of the works. The farmers shall arrange for removal and
conveyance at their own cost as indicated in Appendix to G.O. (Ms.)
No. 50, Industries (MMC.1) Department, Dated:27.04.2017 and this
shall be under the monitoring of the District Collector.
Hand over the water body to the department after completion of
works without any damages to bund, appurtenances.
To ensure that there is no reduction in the original size, extent,
capacity of the water body.
Ensure adherence to all applicable laws and regulations while
implementing the Project.
e Ensure that the work is undertaken as per the terms and conditions
as specified by the Municipal Administration and Water Supply
Department.
6. Monitoring and evaluation
Regular monitoring and evaluation of rejuvenation activities will be
conducted to assess progress towards achieving the objectives at ULB
level.
7. Dispute Resolution
Any dispute arising out of or in connection with this MoU shall be settled
amicably through mutual consultation. In case of unresolved disputes, the
matter shall be referred to arbitration to the Commissioner, Greater
Chennai Corporation / Director of Municipal Administration /Director of
Town Panchayats. The decision of the Commissioner, Greater Chennai
Corporation / Director of Municipal Administration /Director of Town
Panchayats shall be final and binding on both the parties.
8. Intellectual Property
All intellectual property rights generated or developed during the Project
shall be the property of the Municipal Administration and Water Supply
Department unless otherwise agreed upon in writing.
9. Termination
This MoU may be terminated by either party upon written notice, with 15
days’ notice period, to the other party, with or without cause, provided
that such termination shall not affect any obligations already accrued
hereunder.
10. Term and Renewal
This MoU shall be valid for a period of 3 months from the date of
execution. The MoU may be renewed for further periods subject to mutual
agreement between the parties.
11. Entire Agreement & Work completion certificate
This MoU constitutes the entire agreement between the parties with
respect to the subject matter hereof and supersedes all prior or
contemporaneous communications, representations, or agreements,
whether oral or written. Work completion certificate (Annexure-III) is to
be duly signed by Corporate/Firm/Non-Governmental Organizations
(NGOs)/Community Based Organizations (CBOs) /Educational Institution,
Municipal Engineer / Executive Engineer / Regional Executive Engineer
/Chief Engineer of the ULB concerned prior to final payment.
12. Governing Law & Jurisdiction
This MoU shall be governed by and construed in accordance with the laws
of India. The parties agree to submit to the exclusive jurisdiction of the
courts located in the . district for any dispute arising out of
or in connection with this MoU.
IN WITNESS WHEREOF, the parties hereto have executed this MoU as of
the date first written above.
FOR ULB, FOR [Name of Corporates/ Firms /
Non-Governmental Organizations
(NGOs)/ Community Based
Organizations (CBOs)/ Educational
Institutions]
Authorized Signatory Authorized Signatory
Name: Name:
Designation: Designation:
Witness: Witness:
1) 1)
2) 2)
GAGANDEEP SINGH BEDI,
ADDITIONAL CHIEF SECRETARY TO GOVERNMENT
//TRUE COPY//
Thee
(Fis 1@a) sone
& ‘ON OF R
= q
De ment, dated 16.10.202
WORK COMPLETION CERTIFICATE FOR CORPORATE/FIRM/NGO/
CBO/EDUCATIONAL INSTITUTION FUNDS.
As per the memorandum of understanding (MoU) signed with the
Assistant Commissioners/ Deputy Commissioners (in case of Greater
Chennai Corporation), Commissioners/ Executive Officers (in case of
Corporations/ Municipalities/Town Panchayats), Greater
Chennai Corporation (Zone)/ Urban Local Body, Dated: i
Name of the water body in Urban Local
Body, (Habitation) has been rejuvenated by
Corporates/Firms/ Non-Governmental Organizations (NGOs)/Community
Based Organizations (CBOs) /Educational Institutions,
(Unique Id No. ) in District, during the year
at a total expenditure of Rs. , inclusive of the
following items:
1. Earthwork in water spread area …. cum
2. Earth work of Inlet channel (length in m and quantity in cum) and
outlet channel …. (Length in m and quantity in cum)
3. Bund strengthening …. (length in m and quantity in cum)
4. Repair/reconstruction of sluice/ weir …. (indicate the no. of sluices
repaired/reconstructed and weir repaired/reconstructed)
It is certified that all the above works have been completed as per
approved Estimate, Standard specification and as per the conditions of the
MoU signed.
Representative of Corporate /|Municipal Engineer/Regional
Firm/ Non-Governmental | Executive Engineer /Chief
Organizations /Community Based | Engineer of Urban Local Bodies
Organizations/ Educational | / Chief Engineer, Office of
Institution Director of Municipal
Administration/ Director of
Town Panchayats/ Greater
Chennai Corporation.
GAGANDEEP SINGH BEDI,
ADDITIONAL CHIEF SECRETARY TO GOVERNMENT
//TRUE COPY//