Human Resources Management Department

Government of Tamil Nadu spending on human resources management department (Demand No. 35): what was spent, what is budgeted for 2026-27, and what the Budget announced. Every figure traces to a page of an official budget document.

REVENUE
₹368.2 crore
2026-27 RBE
CAPITAL
₹53.1 crore
2026-27 RBE
LOANS
₹3.0 crore
2026-27 RBE
HUMAN RESOURCES MANAGEMENT DEPARTMENT · TOTAL, 2026-27
₹424 crore
All heads of this Demand, RBE

Amount grew from ₹177 crore in 2018-19 to ₹424 crore in 2026-27

Total of all heads of this Demand, ₹ crore. Each year shows the latest stage available: Actual, then Revised Estimate (RE), then Revised Budget Estimate (RBE).

  • Revenue
  • Capital
  • Loans
2018-1918-19
Actual
2019-2019-20
Actual
2020-2120-21
Actual
2021-2221-22
Actual
2022-2322-23
Actual
2023-2423-24
Actual
2024-2524-25
Actual
2025-2625-26
RE
2026-2726-27
RBE
Total by year, ₹ crore
2018-19176.9
2019-20216.9
2020-21215.4
2021-22224.5
2022-23282.4
2023-24266.8
2024-25325.7
2025-26361.4
2026-27424.2
Download data (CSV)Source: Demand No. 35 books and Annual Financial Statements, Government of Tamil Nadu

Source: Demand No. 35 books and Annual Financial Statements, Government of Tamil Nadu. Values in ₹ crore.

Largest allocations

Top five minor heads, ₹ crore.

Minor head2024-25 Actual2025-26 RE2026-27 RBE
2051-00-102 State Public Service Commission143.0148.3151.8
2062-00-105 Other Vigilance Agencies107.0115.4122.9
4070-00-800 Other Expenditure3.32.952.5
2052-00-090 Secretariat32.348.549.6
2070-00-001 Direction and Administration10.913.413.8
Download data (CSV)Source: Demand No. 35 books, Government of Tamil Nadu

Detailed allocation

Loading the explorer…

ABOUT THESE DATA

Series show the latest stage available for each year (Actual > RE > RBE > IBE > BE). Head 2062 is compared with the Annual Financial Statements. Heads 2051, 2052, 2053, 2059, 2070, 2075, 2225, 4070, 7610 are shared with other Demands and are not compared. 17 related data issues

Known data issues

Known gaps and discrepancies in the source documents or between them. Each has a permanent ID. “Documented” means the document itself is wrong and we kept the printed figure; “open” means we have not found the cause.

17 issues
IDStatusWhatTreatment
DQ-D35-0001explainedlatest-stage roll-up does not add up
2051-00-102-AA, 2022-23
Object values add to 1,199,768 thousand but the sub-head shows 1,199,775
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (2 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0002explainedlatest-stage roll-up does not add up
2052-00-092-AV, 2022-23
Object values add to 6,474 thousand but the sub-head shows 6,480
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (3 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0003explainedlatest-stage roll-up does not add up
2062-00-105-AA, 2022-23
Object values add to 807,397 thousand but the sub-head shows 807,405
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (2 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0004explainedlatest-stage roll-up does not add up
2070-00-001-AD, 2023-24
Object values add to 117,215 thousand but the sub-head shows 117,410
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (2 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0005explainedlatest-stage roll-up does not add up
2070-00-003-AH, 2022-23
Object values add to 50,182 thousand but the sub-head shows 50,188
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (2 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0006explainedlatest-stage roll-up does not add up
2070-00-003-AQ, 2019-20
Object values add to 13,935 thousand but the sub-head shows 13,755
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (2 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0007explainedlatest-stage roll-up does not add up
2075-00-800-GZ, 2020-21
Object values add to 346,165 thousand but the sub-head shows 93,484
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (4 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0008explainedlatest-stage roll-up does not add up
2075-00-800-GZ, 2022-23
Object values add to 97,665 thousand but the sub-head shows 97,616
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (14 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0009explainedlatest-stage roll-up does not add up
2225-03-277-BV, 2019-20
Object values add to 5,100 thousand but the sub-head shows 3,600
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (2 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0010explainedlatest-stage roll-up does not add up
2225-03-800-AB, 2018-19
Object values add to 0 thousand but the sub-head shows 28,174
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (0 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0011explainedlatest-stage roll-up does not add up
2225-03-800-AB, 2019-20
Object values add to 0 thousand but the sub-head shows 39,571
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (0 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0012explainedlatest-stage roll-up does not add up
2225-03-800-AB, 2020-21
Object values add to 0 thousand but the sub-head shows 28,973
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (0 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0013explainedlatest-stage roll-up does not add up
2225-03-800-AB, 2021-22
Object values add to 0 thousand but the sub-head shows 31,419
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (0 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0014explainedlatest-stage roll-up does not add up
2225-80-800-AB, 2018-19
Object values add to 28,174 thousand but the sub-head shows 0
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (0 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0015explainedlatest-stage roll-up does not add up
2225-80-800-AB, 2022-23
Object values add to 42,358 thousand but the sub-head shows 42,364
The latest value per code is chosen separately, and for some codes under this sub-head the Actual column is blank, so an earlier-stage figure is used (3 codes here use a different stage from the sub-head). Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0016explainedlatest-stage roll-up differs by rounding
15 sub-head/year pairs
For 15 sub-head/year pairs the object values add to within Rs 5 thousand of the sub-head figure (largest difference 5 thousand = Rs 0.0005 crore)
Each code shows its latest printed stage, and different codes under one sub-head can come from different books, where amounts are rounded separately. Within each demand book every total ties exactly.
Published as is; each code carries its own stage
DQ-D35-0017explainedcode printed in some books but not in between
10 code families
10 codes (with the codes below them) are printed in some books, absent from a book in between and printed again later. Examples: 2051-00-911 'Deduct – Recoveries of Overpayments' (absent from 2021-22 IBE, 2021-22 RBE, 2022-23 BE); 2052-00-911 'Deduct – Recoveries of Overpayments' (absent from 2021-22 IBE, 2021-22 RBE, 2023-24 BE); 2053-00-094-AO-372 'Inspection Cell in the Districts' (absent from 2021-22 RBE, 2022-23 BE). The full list is in the master_codes file (columns books_present and books_list).
Checked against the PDFs: for 6 of 6 family/book absences a text search of the book finds no line with that code. A line with nothing to show in a book seems to be left out of that book; this has not been confirmed with the department.
Each code kept once; presence per book recorded in books_list

Downloads

Human Resources Management Department (Demand 35): budget by code

Every code in Demand 35 from major head down to detail, with full hierarchy and the latest-stage value per fiscal year in Rs crore.

master_code is built only from printed codes. Voted and charged amounts are summed. Where the latest printed figure is nil the value is 0.

Column dictionary (27 columns)
ColumnTypeMeaning
master_codestringUnique alphanumeric code built from printed codes only, for example 2404-00-195-AB-309-03.
levelstringLevel of the code: major, minor, subhead, object or detail.
major_codestringMajor head code.
major_descriptionstringMajor head description.
minor_codestringMinor head code with major and sub-major.
minor_descriptionstringMinor head description.
categorystringState's Expenditure, Central Sector Schemes, or Schemes Shared between State and Centre.
subhead_codestringSub-head code.
subhead_descriptionstringSub-head description.
object_codestringObject code.
object_descriptionstringObject description.
detail_codestringDetail code.
detail_descriptionstringDetail description.
full_path_descriptionstringDescriptions of all levels joined top to bottom.
parent_codestringmaster_code of the level above.
alternate_labelsstringOlder wording of the description, where it changed.
hodstringHead of department code printed in the demand book.
first_bookstringFirst demand book that prints the code.
last_bookstringLast demand book that prints the code.
books_presentintegerNumber of the six demand books that print the code.
books_liststringThe demand books that print the code.
statusstringStatus of the item: for codes, in all books, new, discontinued or intermittent; for issues, documented, explained or open.
fiscal_yearstringFinancial year, April to March, written like 2025-26.
stagestringBudget stage of the figure: Actual (audited), RE (revised estimate), RBE (revised budget estimate), IBE (interim budget estimate) or BE (budget estimate).
amount_crorenumberAmount in Rs crore (1 crore = 10 million rupees).
amount_thousandnumberAmount in Rs thousand, as printed in the source document.
source_editionstringThe budget document the figure was read from, for example 2026-27 RBE.

AFS compared with the Human Resources Management Department demand book

Head 2062 as printed in each Annual Financial Statement and in the matching Demand 35 book: 36 of 36 comparisons agree to within Rs 5 thousand; every other difference is listed as a data issue (see data issues). Heads shared with other Demands are not compared.

Column dictionary (11 columns)
ColumnTypeMeaning
bookstringThe edition of the budget document (AFS and demand book share the edition).
headintegerMajor head: 2404 (revenue), 4404 (capital outlay) or 6404 (loans).
fiscal_yearstringFinancial year, April to March, written like 2025-26.
estimate_typestringBudget stage of the figure (Actual, RE, RBE, IBE, BE).
afs_thousandnumberAmount printed in the AFS, Rs thousand.
demand_thousandintegerAmount printed in the demand book, Rs thousand.
afs_crorenumberAmount printed in the Annual Financial Statement, Rs crore.
demand_crorenumberAmount printed in the Dairy Development demand book, Rs crore.
gap_thousandnumberAFS minus demand book, Rs thousand.
gap_crorenumberAFS minus demand book, Rs crore.
gap_pct_of_afsnumberGap as a percentage of the AFS amount.

Budget announcements

Everything the Budget speech and highlights announce (currently the 2026-27 Revised Budget Estimates): schemes, projects, programmes, reforms, subsidies and policies. One row per announcement per budget year, with the primary amount exactly as printed, its kind (allocation, project cost and so on), the speech paragraph and highlights bullet it comes from, and the Demand(s) for Grants it relates to.

announcement_code is permanent: an announcement keeps its code in every budget year, and one that ends is marked is_current = no, never removed. related_demands links the announcement to the Demand(s) for Grants it relates to; blank means not yet linked. source_document names the budget document, and paragraph or bullet, each row was taken from. Some amounts are the current-year allocation, others the cost of a whole project: always read amount_kind.

Column dictionary (17 columns)
ColumnTypeMeaning
announcement_codestringPermanent ID of the announcement, SCH-2026-nnn. It never changes and is never reused.
budget_yearstringFiscal year of the budget document the row was taken from, for example 2026-27.
namestringScheme, project, policy or announcement name as used on this site.
departmentstringDepartment heading under which the speech and highlights list the item.
item_typestringscheme, project, programme, policy, fund, subsidy, reform, platform, committee, announcement and so on.
related_demandsstringDemand No(s). for Grants this announcement relates to, separated by semicolons (for example 08). Blank if not yet linked.
amount_textstringPrimary amount exactly as printed, for example Rs.139 crore.
amount_crorenumberAmount in Rs crore (1 crore = 10 million rupees).
amount_kindstringWhat the amount is: allocation, cost_stated, project_cost, valued_at, annual, multi_year_cost, capital_outlay, increase, viability_gap, credit_target, grant_sought or none.
other_amountsstringOther amounts printed with the item, each with what it is.
source_documentstringBudget document, and the paragraph or bullet in it, that this row was taken from.
highlights_bulletintegerBullet number in the highlights document.
highlights_pagestringPrinted page of that bullet in the highlights.
speech_paraintegerParagraph number in the budget speech.
speech_pagestringPrinted page of that paragraph in the speech.
is_currentstringyes if the announcement is part of the current budget; no if it has ended or been withdrawn (the row and its code are kept).
source_textstringThe highlights bullet text the entry is based on.

Source: Government of Tamil Nadu budget documents. Extracted and checked by tamilnadudata.org; every figure traces to a page of the cited document.

  • Demand for Grants No. 35, Human Resources Management Department, 2020-21 BE to 2026-27 RBE, Finance Department, Government of Tamil Nadu
  • Annual Financial Statements (Statements I, IA, II, III and Budget at a Glance), 2017-18 BE to 2026-27 RBE, Finance Department, Government of Tamil Nadu
  • Revised Budget Estimates 2026-27: Budget Speech (5 August 2026), Finance Department, Government of Tamil Nadu
  • Revised Budget Estimates 2026-27: Highlights, Finance Department, Government of Tamil Nadu

Data version 1199eb39f910 · generated 2026-11-02

This site uses Google Analytics to count visits. It sets cookies and sends visit data to Google. We do not use it to identify individuals.